Exterior works
- Full re-cladding roof and roof lights
- Cladding sprayed
Internal works
- Floor diamond grind and finish with grey resin floor paint
- Back elevation wall rebuilt
- Full decoration throughout warehouse and offices
- New lighting and electrics installed and certificates (M&E)
- Gas blow heaters installed (M&E).
- Steel columns re-fire boarded and taped and jointed